In accordance with the Energy Transition for Green Growth Act, Ordinance No. 2016-1019 of July 27, 2016, established a legal framework for electricity self-consumption within the Energy Code.
Today, we’re taking a closer look at these operations!
Self-consumption
An individual self-consumption operation occurs when a producer consumes all or part of the electricity generated by their own installation (e.g., solar or wind power) on the same site.
This self-consumption can be total or partial:
- If production is low, the electricity generated is consumed on-site, and the user must rely on the public grid to meet their remaining energy needs.
- If production exceeds demand, the surplus is fed back into the public grid.
Individual self-consumption can also apply to charging infrastructure for electric and hybrid vehicles.

Collective self-consumption
A self-consumption operation is considered collective when electricity is supplied between one or more producers and one or more end consumers linked through a legal entity, provided their withdrawal and injection points are located downstream of the same public medium-to-low voltage transformer substation. Since the structures are quite flexible, associations or cooperatives can also participate.
The conditions for implementing this system have been clarified. Specifically, they:
- Require this operation to be governed by a contract between the relevant public distribution network operator and the legal entity organizing the operation.
- And set a maximum installed capacity of 3 kW for installations required to feed their surplus electricity into the grid if it is not sold to a third party.

Extended collective self-consumption
The Energy Code allows for collective self-consumption operations involving more distant participants, provided the following criteria are met:
- They are connected to the low-voltage network of a single public electricity distribution network operator,
- and the distance between the two furthest participants does not exceed two kilometers.
Upon request, the minister responsible for energy may grant a derogation to this distance within a limit of twenty kilometers , taking into account in particular the isolation of the site and its low population density.
The cumulative power of the production facilities is less than:
- 3 MW in mainland France;
- 0.5 MW in non-interconnected zones.
*For solar energy, the power considered is the peak power.
In the event of surplus electricity being fed back into the grid, there are two support mechanisms for remunerating producers: the feed-in tariff and the feed-in premium. These are awarded either via an open-window system (with tariff levels defined in tariff orders) or through competitive bidding processes (see link at the end of the article).
Feed-in tariff and feed-in premium
Obligation
The feed-in tariff is a support mechanism that consists of the purchase of electricity produced by an authorized supplier, regardless of the wholesale electricity market price. It applies, for example, to photovoltaic panel installations with an installed capacity of ≤ 500 kWp. To benefit from the feed-in tariff for the electricity they produce, operators must apply to EDF or the local distribution company. Contracts are set for a duration of 15 to 20 years. With few exceptions, it is only possible to benefit from a feed-in tariff contract once.

For electricity production facilities with an installed capacity not exceeding 3kW and which are in surplus, the surplus electricity produced is not subject to the feed-in tariff mechanism. It is transferred free of charge to the grid operator to which the production facility is connected. These injections are then allocated to the technical losses of that grid (L. 315-5 and D.315-10).
Feed-in premium:
The feed-in premium is a bonus paid to a renewable energy producer in addition to the sale of the electricity they have produced on the market. Interested producers must apply to EDF, which is required to enter into a contract offering a feed-in premium (for installations located in mainland France).
It concerns larger renewable electricity producers (≥ 500kW), and contracts are set for a duration not exceeding 20 years. Except for specific derogations, renewable energy production facilities can only benefit from the feed-in premium once.

Main tariff orders allowing for preferential purchase conditions for the energy produced:
These orders, as well as the standard purchase contract templates, can be consulted on the website of the Ministry of Ecological Transition and Territorial Cohesion.
Financial support:
A self-consumption bonus is defined by the tariff order of October 6, 2021, for installations under 100kWp that sell surplus energy back to the grid. The application for the self-consumption bonus is processed automatically when the photovoltaic system is connected to the distribution network.
Installations under 3kW are eligible for tax benefits.
Regional subsidies may also be available. Specifically for the development of photovoltaics, an association-led platform supported by ADEME and the government has been created (see link at the end of the article).
However, outside of specific programs for households or the agricultural sector, most projects are not eligible for Energy Savings Certificates (CEE).
Key administrative procedures for photovoltaic installations:
- Prior declaration of works: This is mandatory for ground-mounted installations with a capacity between 3kWp and 250kWp located outside of a protected area (or < 3kWp in a protected area). It is also mandatory for all rooftop installations.
- Building permit application: This is mandatory for ground-mounted installations with a capacity greater than 250kWp located outside of a protected area, or greater than 3kWp in a protected area.
- Connection request: If you intend to sell surplus production, a connection request must be submitted to the grid operator.
- Consuel certificate: This certificate validates the compliance of your installation before it is connected to the electricity distribution network.
Furthermore, even if no planning permission is required, you should check for any local installation regulations, such as the Local Urban Plan (PLU) or the Land Use Plan (POS).
Under the Environmental Code, other procedures must be considered. Consequently, with the exception of rooftop or parking canopy installations, projects are subject to:
- Environmental assessment for installations with a capacity of 1MWp or more, excluding parking canopy installations;
- Case-by-case review for installations with a capacity of 300kWp or more;
Learn more:
- Ministry of Ecological Transition website: Home | Ministry of Ecological Transition and Territorial Cohesion – https://www.ecologie.gouv.fr/
- Non-profit website supported by the government and ADEME for the development of photovoltaics: https://www.photovoltaique.info
- Several CRE calls for tenders have been launched for self-consumption installations to encourage their development: Call for tenders for the construction and operation of electricity production facilities using renewable energy for self-consumption located in mainland France | CRE – https://www.cre.fr/
- ADEME Bookstore: Photovoltaic self-consumption: how to produce electricity and consume it at home? – The ADEME Bookstore – https://librairie.ademe.fr/
- CSTB guide on installing rooftop photovoltaic systems (January 2024): – https://www.ecocites.logement.gouv.fr/
- Lab2051 incubation for collective self-consumption (June 2022): – https://www.ecocites.logement.gouv.fr/
Photo credit: 648812482 @Sasint